Beaumont Hospital

Theatre Upgrade Contract

Project Description

MedProGas were engaged by Bender UK as incumbent gas specialists to complete this highly

challenging and complex project that involved phased works to all 12 no. Theatres within the

hospital. The MedProGas team navigated complex challenges, including management of

multiple phased shut-downs and tie-ins to existing medical gas systems.


MedProGas had to engage with the Client and Bender to ensure that RAMS were generated

to ensure all aspects of tie-ins and shut-downs and backfeeding were fully detailed and

concise.

The med gas systems upgrades enhance patient care, optimize staff facilities, and improve

hospital efficiency, providing cutting-edge medical environments for the community.

The phased works were extremely challenging as multiple parties were involved in the

installation works. Phasing and sequencing the install with the Client within very tight

timelines was key to getting the contract over the line. In some instances, the theatre ceilings

were extremely restrictive with little or no tolerance, adding difficulty and time constraints

into the equation. MedProGas worked with the team and we successfully completed the

turnkey project - with MedProGas commissioning each Theatre on completion, for signoff by

the Client. MedProGas works were completed within-budget delivery while maintaining the

highest standards of quality and compliance.

Client

Bender UK


Main Contractor

Bender UK


Duration

12 Months