Rotunda Hospital

New NICU 


Project Description


MedProGas completed design development, installation testing and commissioning to current BCGA / HTM Standards of the complete medical gases systems to the New Rotunda NICU.

Works involved a highly intensive programme for both isolation / strip-out / tie-in and phased handover of the new area. All works were completed within a restricted site  fully working Maternity Hospital 24/7. The new facility provided a complex arrangement of dual circuitry to 22no. new Cot Positions. New Primary O2 / MA4 and Vac Mains were installed throughout.

Completed works tested / commissioned and handed over by MedProGas with the Client Nominated AP witnessing and signing off to HTM 0201 standards.


R McKenna assumed role of AP witnessing and signing off to HTM 0201 standards to the client's satisfaction.

Client

HSE


Engineering

JV Tierney Assoc


Mech Contractor

Elenfield Construction


Duration

8 months (phased works)